Regular monitoring of key performance indicators is a smart way to keep your ESP running efficiently. Small problems are likely to eventually become big ones, or even de-rate crises, so it makes sense to head off issues at the pass by making best use of the operational data available.

One key indicator that’s often overlooked is the V-I curve (voltage current relationship between T/R sets). Regular monitoring of V-I curves can provide useful insight into why changes in system performance occur over time. From these readings, it’s possible to uncover a variety of problems, such as fluctuations in resistivity, which can be fixed more easily if caught early

While it’s true taking a V-I curve reading requires ramping the T/R set down and back up, which can cause a short opacity spike (especially with outlet fields), the useful data rendered from this short blip is well worth it. Checking V-I curves should be part of your maintenance and troubleshooting routine along with voltage control calibration and resistivity testing.

Despite the potential utility of V-I curve data, almost no-one monitors this key indicator on a regular basis. So, if you haven’t made a New Year’s resolution yet, try this: I will regularly perform V-I curve monitoring and use this information to proactively address ESP problems.

 

Helpful Resources

KnowledgeBase: Troubleshooting

KnowledgeBase: Maintenance

KnowledgeBase: Theory of Operations: Charging

KnowledgeBase: Optimizing Corona Power

Go Back

Baghouse Integration Dramatically Reduces O&M Costs

Fly Ash System

A 1,500 MW Southeastern U.S. coal-fired power plant was able to improve the effectiveness of their fly ash evacuation systems and reduce the costs of operation and maintenance by an expected 50% through improved, integrated instrumentation. ...

Read the White Paper

"We now have a more flexible system that we are expecting to reduce our operation and maintenance costs by 50%. "